Getting the New National Stadium Ready On Time
Guideto Japan
- English
- 日本語
- 简体字
- 繁體字
- Français
- Español
- العربية
- Русский
Preparations are underway in Tokyo and elsewhere in the country for the opening of the Summer Olympic and Paralympic Games on July 24, 2020. The most concerning aspect of these arrangements is, of course, the progress on the New National Stadium, the main venue for the games. The original design proposal by the architect Zaha Hadid was scrapped, even after several revisions, necessitating a sudden rethink; it was only in December 2015 when a concept by Kuma Kengo was adopted as the final design. This state of affairs raises questions about how the delayed construction on the stadium is going.
To find out about the current situation, we visited the offices of the Japan Sport Council, the entity that formally placed the order for the stadium, located in central Tokyo’s Jingū Gaien district. There we spoke with Komatsu Yukio, a deputy department director at the New National Stadium Planning and Construction Bureau, and Tasaka Akihiko, manager of the bureau’s Building Division, which handles the design.
Shortening the Construction Schedule
INTERVIEWER Let’s begin with a progress report on stadium construction.
KOMATSU YUKIO It’s now been twenty-five months since we broke ground in December 2016, and work is proceeding steadily. There have been no significant delays. Provided that nothing really out of the ordinary happens, we should be on track to meet the November 2019 deadline.
INTERVIEWER Walking around the site before this interview, we were impressed to see that much of the steel frame of the roof was in place and a good third of the scaffolding surrounding the exterior wall had already been taken down. The schedule must be pretty tight on a job of this magnitude.
KOMATSU The schedule was fixed from the outset, so from the design stage we were already creating the technologies and techniques we needed to procure materials and shorten the schedule. A much bigger concern for us was the labor shortage, owing to the overall aging of Japanese society on top of the falling number of construction workers in Japan these days. We haven’t had serious problems in this regard either, though.
INTERVIEWER Describe the technologies and techniques you’re using onsite.
TASAKA AKIHIKO For the foundation and the stadium stands, we used preformed ferroconcrete blocks. By installing these instead of pouring concrete onsite, we avoided waiting around for the concrete to set before we could work with it. Similarly, we’re working the steel frame that forms the rooftop beams in two parts: the base frame, which forms the roof’s foundation, and unit frame at the end of the roof structure. That unit frame is further made up of three units, which are assembled on the field.
INTERVIEWER By working simultaneously on the field and on the upper stands, you’re shortening the schedule?
KOMATSU That’s right. The work demands precision, though, to raise up each of the units by crane and connect them to the base frame. The rooftop is supported by 108 steel frames installed in a round shape, and misaligning the positioning by even a few millimeters when the joining work is done has a tremendous impact on the other units. We use laser-sighting and other 3D measurement technologies to line up targets for joining the frames. This has let us reduce alignment errors of the base portions to within 3 millimeters total.
INTERVIEWER Have there been any changes or cost overruns?
TASAKA There are numerous little changes on a typical construction site. We execute a change agreement with the contractors every half term, but given how big this job is, we’ve had hundreds of changes each period, working out to more than 1,000 over the past two years. The schedule is set, however, and the budget does have a ceiling. And we keep adjusting to stick to both.
A Stadium Takes Shape
INTERVIEWER The project is starting to look like a stadium. What’s it like to see design become reality?
TASAKA We’re looking forward to showing to the world the portions of the stadium construction where we’ve incorporated elements of traditional Japanese construction, that is, the extensive use of lumber. It seems to me that this is itself a modern expression of elements of traditional Japanese woodworking construction. It shows a sharp and graceful form, with the edges of the eaves and all.
KOMATSU This will be one of Kuma Kengo’s signature creations, and we’re sweating the details on the construction itself. After all, there aren’t any other stadiums anywhere that give the sense of the presence of wood all around.
INTERVIEWER When one looks up at the stadium while walking around the construction site, the lumber used in the eaves is clearly visible, giving an impression of warmth, of comfort, rather than the inorganic sense that is all too typical of large-scale architecture. In January 2017 there was an announcement that lumber for the project would be procured from all forty-seven Japanese prefectures. Did you succeed in that effort?
TASAKA The contractors proposed using domestic lumber that has obtained official forest certification to build the stadium’s wooden eaves. When we first started the project, there were some prefectures that couldn’t provide this certified lumber, but thanks to the efforts of local governments and businesses to obtain this certification in order to help with the stadium, we did indeed reach that goal.
World-Class Universal Design
INTERVIEWER What about the interior facilities? The seats, the views of the events?
TASAKA We’re getting the word out about our world-class universal design, and we definitely want people to come to the games and experience it for themselves. We conducted a total of twenty universal design workshops over the course of the project, from the design phase right through to the actual construction work itself. We invited fourteen organizations to participate, including disabled persons’ groups, childcare groups, and elder-care organizations. The opinions collected through this process have been reflected wherever possible in the stadium’s planning and construction.
INTERVIEWER What sort of opinions were put forward?
TASAKA Wheelchair seating is commonly anchored in place sideways in these facilities, because of the greater space such seats take up over ordinary seating. However, some people told us they want to sit in the main grandstands to see the games, or to take in the whole field from above. To accommodate these requests, we’ve installed a balance of these various types of seating on each story of the stands, which consist of three layers, accessed via entrances on five stories in all. In like fashion, we’ve installed assistive listening facilities in various areas for use by groups of hearing-impaired persons. Based on our workshop feedback, we’ve also made improvements to things like the heights of tactile boards used to help visually impaired persons navigate the facilities and the positioning of handgrips in the restrooms.
INTERVIEWER Japan has been experiencing heatwaves in recent summers, and there are also concerns about earthquakes and other natural disasters. What measures do you have in place to respond to such incidents?
TASAKA The stands are shaded by the rooftop, and the eaves also efficiently draw seasonal winds into the stadium. Furthermore, above the first and second layers of the stands, we’ve installed fans to facilitate airflow. The breezes created by these features should lower the temperatures in the stands and, combined with the updraft rising off the field as it’s warmed by sunlight, should effectively vent heat from within the stadium into the air overhead.
TASAKA To prepare for earthquakes, we’re building the upper levels with oblique beams and reinforcing steel braces that resist deformation, while the lower levels have a soft first story damping structure, with oil dampers concentrated in certain locations. The seats and the passages have been designed to facilitate rapid evacuation in case of emergency, and we also have facilities for using the stadium as a local disaster recovery site, including standby generators and storage areas containing disaster recovery equipment.
INTERVIEWER The Emperor’s Cup soccer championship, scheduled for New Year’s Day 2020, are slated to be the first major sporting event open to the public at the New National Stadium. That leaves no room for error whatsoever in the schedule, especially when preparations for that game are taken into account.
KOMATSU From a planning standpoint, everything is in order. We’re making safety our primary concern in construction so that accidents, won’t impact the process at all.
(Originally written in Japanese. Reporting and interview photos by Nippon.com. Banner photo: The stadium as it stood on December 1, 2018. Photo courtesy of JSC, with thanks to Sendagaya Intes Bldg.)